ROAD RECONSTRUCTION SCHEDULE

Featured, News

Please see below the schedule for the 2025 Road Resurfacing project:

  • Milling, 4 days from June 30th – July 3rd:
  • Monday, June 30: Montebello Road (village section, Hemion to Lake Rd) and Karsten Drive
  • Tuesday, July 1: Heatherhill Lane
  • Wednesday, July 2: Mile Road (partial, Heatherhill to Viola)
  • Thursday, July 3: Nottingham Drive
  • Paving, 4 days starting July 2nd and 3rd, then 7th and 8th:
  • Wednesday, July 2: Montebello Road (village section, Hemion to LakeRd) and Karsten Drive
  • Thursday, July 3: Heatherhill Lane
  • Monday, July 7: Mile Road (partial, Heatherhill to Viola)
  • Tuesday, July 8: Nottingham Drive

The above schedule is tentative, subject to weather and may slightly change.

Please plan accordingly, thank you!!!

author avatar
Joan Will
There will be REGULAR TRASH PICKUP on Friday, July 4th!
Skip to content