Road Reconstruction Schedule

Featured, News

Please see below the schedule for the 2025 Road Resurfacing project:

  • Milling, 4 days from June 30th – July 3rd:
  • Monday, June 30: Montebello Road (village section, Hemion to Lake Rd) and Karsten Drive
  • Tuesday, July 1: Heatherhill Lane
  • Wednesday, July 2: Mile Road (partial, Heatherhill to Viola)
  • Thursday, July 3: Nottingham Drive
  • Paving, 4 days starting July 2nd and 3rd, then 7th and 8th:
  • Wednesday, July 2: Montebello Road (village section, Hemion to LakeRd) and Karsten Drive
  • Thursday, July 3: Heatherhill Lane
  • Monday, July 7: Mile Road (partial, Heatherhill to Viola)
  • Tuesday, July 8: Nottingham Drive

The above schedule is tentative, subject to weather and may slightly change.

Please plan accordingly, thank you!!!